Location
This project is located at the intersection of Southside Blvd. and Deer Flat Rd. on the south side of Nampa.
Description
The intersection is currently a two-way stop-controlled configuration. East and west traffic on Deer Flat Road is stopped controlled while the north and south traffic is free flow on Southside. The project will reconfigure the intersection into a roundabout.
Need for Project
This intersection is currently configured as a two-way stop-controlled. A roundabout in this location is expected to improve safety and mobility for both the Southside Blvd. and Kuna Rd. corridors. The project will fit the context of a roundabout corridor for Southside Blvd. This corridor currently has roundabouts planned at the intersections of Southside & Lewis, as well as Southside & Kuna.
The process and schedule for the project are currently as follows:
– Design Consultant Selection – September 2020 (Kittelson & Associates)
– Public Meeting – March 4, 2021
– Online Meeting Details:
https://www.zoom.us/join/
Meeting ID: 946 6128 0876
Passcode: 262364
– Concept Report – April 2021
– Preliminary Design – Fall 2021
– Purchase of Right-of-Way – 2022
– Final Design – Fall 2022
– Public Meeting – Spring 2024
– Construction- Spring 2025 to Fall 2025 (seven month duration)
News Releases and Newsletters
Graphics and Displays
– Southside and Deer Flat Concepts – Concept B Selected