Location
This project is located at the intersection of Southside Blvd. and Kuna Rd. on the south side of Nampa.
Description
The intersection is currently a two-way stop-controlled configuration. East and west traffic on Kuna road is stopped controlled while the north and south traffic is free flow on Southside. The project will reconfigure the intersection into a roundabout.
Need for Project
This intersection is currently configured as a two-way stop-controlled. A roundabout in this location is expected to improve safety and mobility for both the Southside Blvd. and Kuna Rd. corridors. The project will fit the context of a roundabout corridor for Southside Blvd. This corridor currently has roundabouts planned at the intersections of Southside & Lewis, as well as Southside & Deer Flat.
The process and schedule for the project are currently as follows:
– Design Consultant Selection – October 2019 (Six Mile Engineering)
– Public Meeting – February 2, 2021
– Online Meeting Details:
https://www.zoom.us/join/
Meeting ID: 978 9076 9215
Passcode: 405157
– Concept Report – March 2021
– Preliminary Design – Summer 2021
– Purchase of Right-of-Way – 2022
– Final Design – Spring 2022
– Public Meeting – Spring 2025
– Construction – Spring/Summer 2029 (six month duration)